РЕФЕРЕНЦИ
Огромен дел од индустријата во Македонија ги користи нашите услуги и решенија.
Експертс е присутен во повеќе од 3000 фабрики, погони и останати потрошувачи во сите делови од индустријата на територијата на Македонија како и на Косово.
Најзначајни проекти на изведени ‘клуч на рака’ се:
TURN KEY Installations
Client | Place | Total air delivered | Lead time | Remarks |
JUGOHROM Ferroaloys | TETOVO Jegunovce | 80m3/min at 10 bar | 12 weeks after delivery | Compressed air station complete with dust collectors, recirculation ducts, automatic regime of operation on the temperature and pressure, compressor controller for automatic operation of compressors, dryers and filters. Piping of steel pipes DN100. |
REK Oslomej-power plant |
Kicevo | 43m3/min at 7,5 bar | 10 weeks | Compressor with pipework of welded steel pipes DN100, water cooled, el.cabinet and electrical connection |
VITAMINKA | PRILEP | 46m3/min at 10 bar | 12 weeks | Complete compressed air solution, equipment compressors, air treatment, receivers, electrical and mechanical connection, PP piping of 2” for complete factory, 600 meters length, with hoses and connections to each machine |
TE-TO | Skopje | 16m3/min |
12 weeks | Delivery, supervising of complete installation and commissioning |
PROTOTIP | Skopje | 5m3/min at 10 bar |
12 weeks | Complete compressed air solution, equipment compressors, air treatment, receivers, electrical and mechanical connection, PP piping of 2” for complete factory, 600 meters length, with hoses and connections to each machine |
VARDAR DOLOMIT | Gostivar | 6m3/min at 10 bar | 6 weeks | Compressed air room along with equipment, installation, electrical connection |
FENI Industry | Kavadarci | 172m3/min at 7,5 bar |
12 weeks | Supervising of complete installation and commissioning |
KEMET | TIRZ SKOPJE | 35m3/min at 10 bar |
13 weeks | Complete compressed air solution, equipment compressors, air treatment, receivers, electrical and mechanical connection, ALUMINUM piping of DN100” for complete factory, 200 meters length, closed system for water cooling with heat exchangers |
JOHNSON CONTROLS | TIRZ STIP | Aluminum piping |
5 weeks | Complete ALUMINUM piping D110, D63, D25 with fittings, coupling, valves, commissioning |
AKTIVA | STIP | 3,2m3/min + piping | 2 weeks | Compressed air room along with equipment, installation, PP piping D50 for complete factory |
MARQUARDT | TIRZ VELES | 40m3/min + piping | 8 weeks | Complete compressed air solution, equipment compressors, air treatment, receiver and mechanical connection, ALUMINUM piping of D110,D63,D50,D32,D25 for complete factory |
ARC MAKEDONIJA |
TIRZ SKOPJE | 25m3/min + piping |
8 weeks | Complete compressed air solution, equipment compressors, air treatment, receiver and mechanical connection, ALUMINUM piping of D110,D63,D50,D32,D25 for complete factory |
CONDEVO | TIRZ STIP | 51m3/min+ piping |
6 weeks | Complete compressed air solution, equipment compressors, air treatment, receiver and mechanical connection, ALUMINUM piping of D110,D63,D50,D32,D25 for complete factory |
GENTHERM Phase 1,2,3 |
TIRZ PRILEP | 45m3/min + piping |
3×4 weeks | Complete compressed air solution, equipment compressors, air treatment, and mechanical connection, ALUMINUM piping of D110,D50, for complete factory |
KROMBERG & SCHUBERT |
Zabeni Bitola | Aluminum piping |
5 weeks | Complete ALUMINUM piping D80, D63, D25 with fittings, coupling, valves, commissioning |
ODW Elektrik | TIRZ Struga | 6,4m3/min+piping | 3 weeks | Complete compressed air solution, equipment compressors, air treatment, and mechanical connection, ALUMINUM piping of D80,D25, for complete factory |
ADIENT AUTOMOTIVE | TIRZ Strumica | 14m3/min+ piping | 3 weeks | Complete ALUMINUM piping D110, D80, D63, D25 with fittings, coupling, valves, commissioning |
MURAT CABLO | TIRZ SKOPJE 1 | Aluminum piping | 2 weeks | Complete ALUMINUM piping D63, D20 with fittings, couplings, valves, compressor room. |
MAKDIA | TIRZ SKOPJE 1 | 6m3/min+piping | 3 weeks | Complete compressed air solution, equipment compressors, air treatment, receiver and mechanical connection, PPR piping of D63,D32 for complete factory |